Part of the Arshya group: IBRFittings.com | ArshyaFittings.com
1 September 2026 · Documentation · Delivery · EN 10204 · PED · IBR

The Complete Pipe Fitting Delivery Documentation Package: What to Demand and Why

A pipe fitting delivery that arrives without the correct documentation is incomplete — even if the fittings themselves are perfectly manufactured to specification. Documentation is not a bureaucratic afterthought; it is the evidence base that allows the fitting to be accepted into a quality management system, installed in a regulated piping system, and traced throughout its service life. Different projects and jurisdictions require different document sets. This article outlines the full document package hierarchy so procurement engineers can specify exactly what is needed on the PO.

Minimum Documentation (All Orders)

  • EN 10204 2.2 Declaration of Conformity: Manufacturer's statement that the supply conforms to the order. Not a test certificate — contains no actual test data. Acceptable only for non-critical, non-regulated service.
  • EN 10204 3.1 Inspection Certificate: Actual test data (chemistry, tensile, elongation, hardness if tested) countersigned by the manufacturer's AIR. The standard minimum for industrial process piping.
  • Packing List / Delivery Note: Quantity, size, grade, and heat number(s) per line item. Must match the 3.1 certificate exactly.

Additional Documents by Service Type

Service / RequirementAdditional Document Required
PED Category III–IV (EU)EN 10204 3.2 (TPI countersignature) + Declaration of Conformity to PED 2014/68/EU (DoC)
NACE MR0175 sour serviceHardness test report (HRC or HBW per fitting) + heat treatment record
Alloy steel (P11/P22/P91/P92)Heat treatment record (time-temperature chart with furnace ID and thermocouple positions)
Cryogenic serviceCharpy impact test report at the specified test temperature
PMI requirementPMI/XRF report per fitting or per heat (as agreed)
NDE inspected fittingsPT/MT/UT/RT report with acceptance criteria and inspector certification (ASNT Level II)
TPI witnessedTPI witness report (TÜV / Lloyd's / BV / DNV) confirming inspection scope and acceptance
IBR-notified (India)IBR Form III-B signed by the Inspecting Authority
Oxygen-clean serviceCleaning certificate per ASTM G93 / CGA G-4.4 — NVR test result

How to Specify on the PO

State each required document explicitly in a "Documentation Requirements" section of the PO. Do not rely on blanket statements like "full documentation required" — they are unenforceable because "full" is undefined. Instead, list each document by name: "EN 10204 3.1 certificate; heat treatment record per fitting heat; Charpy test report at −46°C per heat; hardness test report HRC per fitting." Add: "All documentation to be submitted with the shipment — do not dispatch without complete documentation." For PED: "Declaration of Conformity to PED 2014/68/EU Annex III Module H to be included — fitting must be CE-marked."

Consequences of Missing Documents

A fitting received without its required documentation cannot legally be installed in a PED Category III–IV system without a formal deviation process. In IBR-notified steam service, an uninspected fitting is a statutory violation of the Indian Boilers Act. In NACE sour service, a fitting without hardness records cannot be verified as compliant — it must be quarantined or tested destructively. The cost of recovering missing documents (chasing the supplier, performing additional tests, raising formal deviations) consistently exceeds the cost of specifying correctly at the outset.