PWHT for CrMo Pipe Fittings: Temperature Ranges by Grade

Post-weld heat treatment is mandatory for all CrMo alloy steel pipe fittings — without exception. The temperature range varies by grade, and getting it wrong permanently damages the material.

Why PWHT Is Mandatory

CrMo steels transform to martensite in the heat-affected zone during welding. Weld martensite is hard (potentially >350 HBW), brittle, and susceptible to hydrogen-induced cracking. PWHT tempers the martensite: it restores toughness, relieves residual stress, and creates the stabilised microstructure required for long-term creep service. Without PWHT, the fitting will crack — either immediately during cool-down or in early service.

PWHT Temperature Ranges by Grade

GradeEN W.Nr.PWHT Temp (°C)Min. Hold Time
P11 / 1¼Cr-½Mo1.7335690–730≥1h/25mm, min 1h
P22 / 2¼Cr-1Mo1.7380700–750≥1h/25mm, min 1h
P5 / 5Cr-½Mo1.7362720–760≥1h/25mm, min 2h
P9 / 9Cr-1Mo1.7386720–760≥1h/25mm, min 2h
P91 / 9Cr-1Mo-V1.4903745–775≥1h/25mm, min 2h
P92 / 9Cr-2W1.4901750–780≥1h/25mm, min 2h

Common PWHT Errors

  • Temperature too low: Retained hard martensite, HAZ hardness exceeding 265 HBW — the most common non-conformance on CrMo weld inspection.
  • Exceeding the maximum: For P91 and P92, the Ac1 transformation temperature is approximately 800°C. Exceeding the PWHT upper limit risks re-austenitising part of the HAZ, which then re-transforms to fresh martensite on cooling — worse than no PWHT at all.
  • Using P91 procedure on P92: The temperature windows overlap (745–775 vs 750–780), but P91's ER90S-B9 filler is incompatible with P92 base metal. Separate WPS qualification is mandatory.
  • No chart recording: PWHT without thermocouple attachment and chart recording is not accepted under any major code. The chart is a permanent QC document.

Preheat Requirements

All CrMo grades require preheat before welding and maintenance of inter-pass temperature throughout: P11/P22 — typically 150–200°C; P5/P9 — 175–230°C; P91/P92 — 200–250°C. The joint must not be allowed to cool below preheat temperature during the welding sequence.